July 21, 2022
Next week (July 27 through 29), a portion of the Village of Montgomery Bike Path will be seal coated by a contractor procured by the Village. The work slated focuses primarily on the Lakewood Creek subdivision and adjacent connections. Upcoming path improvements are on the Village's west side between Rt. 30 and Orchard Rd. After the seal coating, the bike path area will require 24 hours to cure, and try limiting bike path use in the Village next week.
The tentative schedule (weather permitting) is as follows:
July 27
- Concord Connection
- Manchester to Deerpoint Connection
- Civic Center and Griffin
July 28
- Lakewood Creek between Rt. 30 and Providence
July 29
- Lakewood Creek south between Providence and Concord
- Concord west to Gordon
PROJECT RESOURCES
2022 Bike Path Sealcoating Schedule & Map